- The Milestone Report is accessible from the Main Menu, under the Production stack.
- Under a status column, the Milestone Report may display a red number in a circle. This icon communicates the number of Issues that should be resolved prior to a System Element achieving that milestone (i.e., status).
- Selecting that red number will open a Milestone Report Details panel, which includes an Issues section.
- Each Status added to the Milestone Report grid view receives an associated filter, titled "<Status> : Completion". This allows Users to filter according to the Schedule Compliance for that status.
- Under each status, the Milestone Report displays icons that communicate whether a System Element reached a status by the Planned Date, after the Planned Date, or with no Planned Date set.
Schedule Compliance Icon Summary
Icon | Schedule Compliance | Description |
---|---|---|
Not Planned | No Planned Date has been set for the System Element Status. | |
Late | The System Element transitioned into the status after the Planned Date, or the System Element has not transitioned into the target status and the Planned Date has already passed. | |
On Time | The System Element transitioned into the status before the Planned Date. | |
On Time - Pending | The System Element has not transitioned into the status and the Planned Date is still in the future. | |
n/a | On Time - At Risk | The System Element has not transitioned into the status, the Planned Date is still in the future, but a dependency status is late. ** Currently Users are able to Filter according to this condition, but the grid view does not display an icon for "On Time - At Risk" Schedule Compliance. |
...