- Service Budgets View - Accessible from the Main Menu (see Finance stack), the Service Budgets grid view presents all configured Service Budgets a user has privileges to access.
- Filter this view by Contract, Name, Start/End Dates, Location, Case Category and/or Total Awarded amount.
- Quickly glean essential budget-tracking information, including:
- Total Awarded amount
- Uncommitted Balance remaining,
- Unrequested Balance remaining, and the
- Closed costs, Committed costs and Pending Requests upon which those calculations are based.
- Use the New widget, atop the grid view, to create a new Service Budget.
- Contract Details Display - Once a Service Budget is created for a Contract, a summary of that budget will be displayed within the Contract Details panel. Scroll to the Service Budgets section near the bottom of the panel.
- Case Forms and Details Display - Case forms and details now provide users instant access to real-time Service Budget information:
- The New/Update Case forms will now present a Budget field, from which the user can select the desired Service Budget.
- This field presents the traditional magnifying glass icon, which provides the user access to all Service Budgets available for selection.
- Each Service Budget option also displays the budget's current balance information, to help ensure adequate funding is available for the requested work.
- This field presents the traditional magnifying glass icon, which provides the user access to all Service Budgets available for selection.
- Once a Service Budget is associated with a Case record:
- The Service Budget association will be prominently displayed near the top of the Case Details panel.
- Positioning your mouse over that Service Budget value will present a pop-up with a current budget summary.
- Case Update forms will present the associated Service Budget, as well as its balance summary, within the Estimated Cost section of the form.
- The Service Budget association will be prominently displayed near the top of the Case Details panel.
- The New/Update Case forms will now present a Budget field, from which the user can select the desired Service Budget.
- Case Category Configurations - Several new Case Category configurations impact the way Cases interact with Service Budgets:
- Billing Type - InfraLink's Service Budget feature supports two billing types, time & materials or firm fixed price. These billing types vary in the way that costs are applied against the budget in Closed statuses:
- T&M - The Service Budget applies the Estimated Cost against the Service Budget in Committed statuses, and then applies actual costs (Case-logged Material, Billable Labor and Misc Expense costs) against the Service budget in Closed statues.
- FFP - The Service Budget applies the Case's Estimated Cost against the Service Budget in both Committed and Closed statuses.
- Estimate Type - This configuration controls how a Case's Estimated Cost value is entered:
- Direct Entry (most common) - The user manually populates the Estimated Cost field during Case creation or update.
- Excel File - The Estimated Cost value is pulled from a properly formatted field within an uploaded Excel spreadsheet.
- Require Service Budget Selection - When enabled, a user cannot transition a Case into a Committed status without a Service Budget selection.
- Enforce Service Budget Funding - Optional when Require Service Budget Selection is enabled. When enabled, this feature prevents a Case from entered entering a Committed status when the Case's Estimated Cost exceeds the Service Budget's available balance.
- Billing Type - InfraLink's Service Budget feature supports two billing types, time & materials or firm fixed price. These billing types vary in the way that costs are applied against the budget in Closed statuses:
- Case Status Business Logic Configurations - Whether or not a Service Budget considers Costs as committed or closed depends on the Case's current status.
- The New/Edit Case Status forms include two unique Business Logic settings, upon which that determination is made:
- Committed Work
- Is a "Closed" status
- Service Budget Permissions - The following new Permissions apply to Service Budget privileges at the Contract and Case level:
- Contracts → Service Budget → Create, Read and Update
- Cases → General → Select Case's Service Budget
- Note: Users must also have Contracts → Service Budget → Read Permission to see the Service Budgets available for a given Case.
...