...
From the operational standpoint, it is a good idea to establish a naming convention for PM groups to make it easier for the IMMS InfraLink administrators and users to navigate the PM schedule. It is common to include references to the contract, location, system and/or system element type being maintained, and frequency in the PM group name.
...
Selecting PM Group Contract
Any work tracked in IMMSInfraLink, including PMs and similar activities, must be associated with a contract, which, in turn, drives the workflow, access privileges, and what equipment the work may be related to. As such, a PM group must be associated with a contract, and the contract association defined for the PM group will also apply to all cases and work tickets, if defined, generated based on the PM group definition.
...
Note |
---|
To prevent discrepancies, IMMS InfraLink will not allow changing the contract selection for an active PM group. If you need to make changes to such PM group, first change the status to "Inactive" and save the change. Then, start editing the PM group again and modify the contract selections. Change the status back to "Active" after all configuration changes have been completed. |
...
The status of the PM group determines whether or not the PM generator will process the PM group definition and generate or update the corresponding PM occurrences (represented by cases in IMMSInfraLink). The status also determines whether or not changes to the schedule and scope components of the PM group are allowed.
IMMS InfraLink supports the following PM group status options:
...
In general, the PM schedule defines when the work is required to be completed. The IMMS InfraLink PM generator will create a PM case for each due date calculated based on the schedule defined by the PM group. This is best explained using an example.
For example, if PM group is defined for work to be completed every 2 weeks by Thursday starting on March 4, 2016, the IMMS InfraLink PM generator will generate a PM case with the due date of March 4, 2016, another PM case with the due date of March 18, 2016, yet another PM case with the due date of April 1, 2016, and so on.
...
Additional schedule-related settings included in the PM group define when the schedule becomes effective, when it stops being effective, how far in advance the PM occurrences will be generated by the IMMS InfraLink PM generator, and, finally, how much time the project team will be given to complete each PM.
...
Setting | Description |
---|---|
Schedule work <N> intervals in advance | In order to assign work to technicians and manage the team's workload, you want the PM cases for the specific occurrences to be generated. At the same time, you don't want to generate cases for the PM occurrences that are too far in the future, as they may likely change and will only clutter the views in the system. This configuration setting allows you to control how far in advance the PM cases will be generated. For example, if the PM group is defined as weekly, and this setting is set to 2 (i.e. "Schedule work 2 intervals in advance"), then each time the IMMS InfraLink PM generator runs, it will make sure the PM cases are generated for the next two weeks. |
Schedule Type | This setting defines the recurrence pattern:
|
Schedule Details | After the schedule type is selected, IMMS InfraLink will allow you to specify the frequency and to further refine when the PM completion will be due. Specifically,
|
Schedule Range | This section contains a few additional parameters that define how the work is scheduled and when it will be expected to be performed.
|
...
Note |
---|
To prevent discrepancies, IMMS InfraLink will not allow changing the schedule of an active PM group. If you need to make changes to such PM group's schedule, first change the status to "Inactive" and save the change. Then start the Edit function again and modify the schedule settings. Change the status back to "Active" after all schedule configuration changes have been completed. |
...
- Specifying the system elements, that the work is to be performed on, and
- Specifying the work form, which defines the work to be completed for each system element.
IMMS InfraLink provides two options for specifying the system elements to be included in the scope of the PM group:
- Specifying the system element type and location, so that system elements can be selected automatically. This option is practical when the system element selection is easily defined by location and type (e.g. camera). The main benefit of this option is that new system elements installed during the course of the project will be automatically added to the PM, as long as they meet the specified criteria (location and type).
- Select individual system elements. This option is practical, when the system elements need to be selected based on a somewhat complex criteria (e.g. all items of a particular kind mounted at a particular height and requiring certain equipment to complete the work). The drawback of this option, however, is that IMMS InfraLink will not automatically pick up new items that may be installed and need to be covered by the PM.
...
Column Name | Description |
---|---|
Device_ID | Required. Specify the system element name, exactly as it is shown in IMMSInfraLink. The upload function uses the name to find the system element to be added to the PM group. |
Location | Optional. Specify the location path, e.g. "/Area 1/Building 2/Room 123". If the location is specified, the IMMS InfraLink will look for the system element with the name matching that specified in the Device_ID column and with the location matching the specified one. Note, the location path is added to the path specified as the "Base Location" on the file upload form. For instance, if the Base Location is specified as "USA / VA" and the system element location included in the file is specified as "Sterling/LG4/300", IMMS InfraLink will look for system elements located at "USA / VA / Sterling / LG4 / 300". |
Form_Name | Optional. You can use the column to specify the work form to be used for the particular system element. The specified form name must match that stored in IMMSInfraLink. Note, if there's only one work form defined for the particular type of system element, you do not need to specify the form name in the file, as it will be selected automatically. |
...
If the PM group is no longer needed and the PM generator should not schedule work based on the group's definitions, you can change the group status to "Inactive", as described in the "Defining PM Group" section above. Inactive PM groups are not processd processed by the PM Generator.